Energy Storage Project

Energy Storage Project

DATS Install3Irvine Ranch Water District is working with Advanced Microgrid Solutions to install the nation’s largest network of energy storage systems ever installed at a public water agency. This award-winning project enables the district to store energy, making it available when demand for power from the grid is at peak levels and the cost for electricity is higher. Drawing from these stored energy sources saves the district more than $500,000 a year in energy costs and helps to ease the overall burden on the grid when demand is high.

The pumping, treatment and distribution of water accounts for nearly 20 percent of the total electricity consumed in California, according to the California Energy Commission. IRWD’s Energy Storage Project helps to ease peak energy demands, decrease energy costs for the district and reduce its overall carbon footprint.

The 7 MW/34 MWh network will use Tesla batteries installed at 11 of IRWD’s largest and most energy-intensive facilities: two water recycling plants, three water treatment plants and six high-energy pumping stations. These energy storage systems will be linked together as a network, providing real-time tracking and operational flexibility in responding to Southern California Edison requests for demand reduction.

IRWD is a national leader in sustainability and energy efficiency. In 2015, the district commissioned a groundbreaking study to examine the average amount of energy needed to transport, treat and deliver water to customers on a per unit basis (kWh/AF). Each facility – a pump station or treatment plant, for example – has its own “energy intensity.” The study provides IRWD with a complete view of its water-related energy use and will be paired with the energy storage systems to better evaluate and reduce the district’s energy consumption and costs. This is the first instance of a public water agency actively commissioning such research.

Project Updates+

Week of Oct. 15:

Batteries will be delivered Oct. 17 to the Irvine Desalter PTP facility. Power was shut down last week to make the electrical interconnection at Wells 21 and 22, and a shutdown of power is scheduled for this week for the interconnection at the Los Alisos Water Recycling Plant. Lockheed Martin batteries will be delivered to the Baker Water Treatment Plant next week.

Week of Sept. 10, 2018:

The subgrade for the battery packs at the Irvine Desalter PTP facility is being prepared, and the plant will be de-energized on Oct. 9 for construction work. Tesla battery packs were delivered last week to Wells 12 and 22 treatment plant. Electrical requirements are being reviewed at the Los Alisos Water Recycling Plant to minimize trenching for conduits. Underground excavation has begun at the Baker Water Treatment Plant to construct the battery platform.

Week of Aug. 27, 2018:

Construction continues at the Irvine Desalter PTP, Wells 21 and 22 Treatment Plant and LAWRP, and battery packs for each site are scheduled for delivery later this month. All three sites are anticipated to be placed into service in October. Construction at the Baker Water Treatment Plant is expected to start in mid-September.

Week of Aug. 12, 2018:

Construction has started at the PTP and 21/2 WTP site. at MWRP, a customer portal is being set up so staff can monitor performance of the battery system. Construction at LAWRP began this week, and partners are in discussion on the project for the Baker Water Treatment Plant.

Week of July 30, 2018:

The energy storage system at the Michelson Water Recycling Plant went online on Aug. 1 and started charging and discharging batteries. Pre-construction work is ongoing at other locations.

Week of July 23, 2018:

Design and construction activities for the remaining energy storage system sites is ongoing, with the design of the Baker site now completed. Pre-construction meetings are scheduled next week for the LAWRP, Potable Treatment Plant, and Wells 21 and 22 Desalter facilities. Final testing of the batteries at the Michelson Water Recycling Plant is underway.

Week of June 4, 2018:

Pre-construction meetings have been scheduled, and work is to begin at the PTP and 21/22 WTP sites in the next few weeks. Plans for an installation at LAWRP are still under review. Energy generation projects at Baker WTP are ongoing and design drawings are being reviewed.

Week of May 21, 2018:

The commissioning process has commenced at the Michelson Water Recycling Plant facility. Construction of the battery systems at Wells 21 and 22 and Potable Treatment Plant will begin within the next month, with construction of the LAWRP system beginning shortly thereafter. A photovoltaic system is being designed at the Baker water treatment plant to interconnect with the battery system. Construction at Baker will begin in October.

Week of May 14, 2018:

The startup and commissioning process has begun for the MWRP site. A preconstruction meeting for the PTP/WTP project will be scheduled soon. Biweekly communication on the Baker portion of the project has commenced. 

Week of April 23, 2018:

A preconstruction meeting will be scheduled in a couple of weeks for the PTP/WTP site, and staff is collecting data on design and schedule constraints for the Baker treatment facility.

Week of April 09, 2018:

Advanced Micro Systems and Tesla have started the commissioning process, which will take several weeks.

Week of April 5, 2018:

Batteries have been delivered and connected. Tesla arrived in late March to begin testing and commissioning. The next facility designated for the Energy Storage system will be the Los Alisos Water Recycling Plant, with construction to start in May.

Week of Feb. 19, 2018: 

Tesla battery packs are scheduled to arrive at the Michelson Waster Recycling Plant in early March.

To date, the systems have been installed at the following locations:

Deep Aquifer Treatment System

Project Map+

Coming soon

Latest News

happy-to-see-green-thank-our-purple-pipes
Happy to See Green? Thank Our Purple PipesLet’s be honest. We love our treelined streets, verdant medians and common areas that define the Irvine Ranch Water District. And while other communities are cutting back on their landscaping, ours continues to flourish. Since 1963, IRWD has been implementing a...
chilling-with-recycled-water-irwd-and-uci-team-up-to-save-80-million-gallons-of-drinking-water-a-year
Chilling with Recycled Water: IRWD, UCI Save 80 Million Gallons of Drinking Water a YearUC Irvine and Irvine Ranch Water District officials toss ceremonial buckets of water into the cooling towers to kick off the new project. (Shown here, right to left, are UCI Associate Chancellor for Sustainability Wendell Brase, IRWD Board President Douglas...
how-the-irwd-team-safeguards-your-water
How the IRWD Team Safeguards Your WaterThanks to all of the IRWD customers who joined us July 10 for our Tap Water 101 community workshop. If you missed it, check out our new 3-minute video, “Journey of a Water Sample.” You’ll tag along with real IRWD...