Week of March 20: Work will continue on the wall reinforcement for the reservoir, weather permitting, with concrete pours to follow.
Week of March 13: Work will continue on the forms for the reservoir walls.
Week of March 6: Crews will be working on forms for the wall assembly.
Week of Feb. 27: Pouring of the reservoir floor is scheduled to take place this week, weather permitting. Once that is completed, forms will begin to be installed to pour the walls.
Week of Feb. 20: Rebar installation will be completed this week, followed by the setting of seismic cables. Pouring of the reservoir floor is expected to take place in late February.
Week of Feb. 13: Work will begin this week on laying the foundation and floor for the reservoir.
Week of Feb: 6: Prep work will be completed this week.
Week of Jan. 30: Work will continue on prep work to install the liner.
Week of Jan. 23: Work will begin this week to trench and install the reservoir liner, and continue into next week.
Week of Jan. 16: Under-tank construction is continuing this week.
Week of Jan. 2: Pipe work will continue this week, followed by the installation of encasements to protect the piping.
2022
Week of Dec. 26: Work will be continuing this week on undertank piping.
Week of Dec. 19: On-site construction will continue this week. No work will take place on Dec. 23. 26 and 30.
Week of Dec. 12: The installation of under-tank piping will continue as weather permits, with pipe encasements beginning next week.
Week of Dec. 5: Work will begin this week to install under-tank piping.
Week of Nov. 21: The access road to the site is being demolished this week, and grading and potholing will also continue.
Week of Nov. 14: Interim grading will be done to prepare the site for construction.
Week of Nov. 7: Potholing work will be starting to identify underground utilities. That work is expected to be completed in mid-November.
Week of Oct. 24: Demolition work is being done as a part of the project. There will be no impact on services, which will continue to be provided throughout the duration of the project.
Week of Oct. 10: Construction began this week with the setup of equipment and temporary facilities, and the installation of a construction fence.