2025:
August: The County of Orange is scheduled to begin work on the bridge this fall. IRWD contractors will return to relocate the pipeline to a permanent position in March, 2026.
June: Pipeline work will be completed, and concrete will be installed at key locations to protect it.
May: Work will begin to relocation water pipeline currently attached to the bridge.
April: Construction is scheduled to begin on Monday, April 7. A temporary water shutdown is scheduled from 8 a.m. to 4 p.m. Thursday, May 1, to establish a temporary water line in anticipation of the upcoming demolition of the southern section of the bridge. This temporary interruption of service will affect residents on Silverado Canyon Road between the western and eastern access points to Oak Lane.